The Nigerian Upstream Petroleum Regulatory Commission has warned holders of underperforming oil and gas licences that their acreage may be revoked if they fail to meet approved work commitments. A circular signed by Chief Executive Oritsemeyiwa Eyesan on 14 September 2026 requires affected licensees to disclose their compliance status by 31 October 2026, identify obstacles to operations and present revised execution plans, Nairametrics reported.
Who is affected
The directive covers licensees from three exercises: the 2020 Marginal Field Bid Round, which resulted in 50 Petroleum Prospecting Licences; the 2022/2023 Mini Bid Round; and the 2024 Licensing Round. At least 62 successful awardees are involved.
Legal basis
The Commission cited sections 77, 78 and 88 of the Petroleum Industry Act 2021, together with the default and revocation provisions in sections 96 and 97. The PIA’s “drill-or-drop” approach ties the retention of acreage to the performance of work programmes. Enforcement options identified include refusing licence extensions, requiring relinquishment of acreage, calling on work performance securities and starting revocation proceedings.
The regulator’s position
The circular states that “the Commission’s objective is to increase production, not forfeiture”. It acknowledges that licensees may face obstacles including financing, rig availability, insecurity, community relations, infrastructure, regulatory approvals and partnership disputes, but adds: “Internal disagreement will not excuse failure to meet licence obligations.”
Get the next Meridian Briefing. Every Thursday at 11:00 WAT.
Why it matters
Many marginal field awardees in 2020 were small consortia that have struggled to raise capital. The circular creates a deadline that will prompt farm-outs, joint ventures and sales of participating interests, as well as disputes among co-venturers. Revocation under section 97 is subject to procedural requirements, including notice and an opportunity to remedy default, and affected parties may challenge decisions that do not follow them.
Licensees should document force majeure and third-party causes of delay, reconcile work programme obligations with licence terms, and consider whether a revised plan with credible funding is achievable before 31 October. Financiers holding security over licence interests should assess exposure to relinquishment or revocation.