An International Chamber of Commerce tribunal seated in Paris has rejected in full a claim by Sunrise Power and Transmission Company against the Federal Republic of Nigeria arising from the Mambilla hydropower project. The final award is dated 17 September 2026 and was made public the following day.
The claim, reported at US$400m, was brought under a 2020 settlement agreement and its addendum. It comprised a US$200m settlement sum and a further US$200m described as a default sum. Reported with interest, the exposure was about US$680m.
The tribunal and the costs order
The tribunal was chaired by Melanie van Leeuwen, with Stavros Brekoulakis and Simon Nesbitt as co-arbitrators. Nigeria was represented by Paul Hastings, with a team that included Elizabeth Oger-Gross and Tolu Obamuroh, according to Lawyard and The Will.
African Law & Business reports that the tribunal found Nigeria was not bound by the 2020 settlement because it had not been properly approved by the government, and that Sunrise and its owner, Leno Adesanya, were ordered to pay 75% of Nigeria’s costs with interest at 10% a year, compounding annually. Lawyard reports that the tribunal held Mr Adesanya personally bound by the arbitration agreement, which exposes him directly to the costs order. Former Presidents Olusegun Obasanjo and Muhammadu Buhari testified for Nigeria.
Get the next Meridian Briefing. Every Thursday at 11:00 WAT.
Counsel
For Nigeria: Paul Hastings, through partners Elizabeth Oger-Gross and Tolu Obamuroh, who joined the firm’s Paris office from White & Case, and the Nigerian firm ALP NG & Co, through senior partner Olasupo Shasore and partner Oyinkansola Badejo-Okusanya, who were instructed in 2017. For Sunrise: Clifford Chance, through partners Alexandros Panayides and Jason Fry KC, with the Nigerian firm G Elias and the French firm Solon. The claim was backed by the litigation funder Burford Capital, according to African Law & Business.
The tribunal assessed Nigeria’s legal fees and expenses at about US$11.82m. Lawyard reports that US$2.5m is to be met from funds held in escrow by the ICC and that Sunrise was ordered to pay the balance of about US$9.32m, with interest at 10% a year, compounded, from notification of the award until payment. The Will reports that the arbitration costs of US$1,656,500 were allocated 75% to Sunrise.
What was decided, and what was not
The award concerns the second of two arbitrations. The first was commenced on 10 October 2017 and, according to Lawyard, sought about US$2.354bn in damages, a figure reported at more than US$2.7bn with interest. Several reports combined the two sums into a headline exposure of US$3.38bn.
The Rio Times notes that the government has not publicly set out the status of the larger claim. Readers should therefore treat reports that Nigeria has defeated a US$2.35bn or US$3.38bn claim with care: the published award, as reported, disposes of the claim under the 2020 settlement agreement.
Background
The dispute traces to a 2003 agreement for a 3,050 megawatt hydropower plant in Taraba State, then described as a project of about US$6bn. By 2021 the project had been rescoped to around 1,500 megawatts at an estimated cost of about US$4bn, according to Lawyard.
The authority behind the underlying commitments has been contested for years. Former President Olusegun Obasanjo has said ministers lacked power to approve projects of that scale without presidential consent, and the late President Muhammadu Buhari denied authorising the 2020 settlement, according to reports of the proceedings.
The government’s position
In a State House statement on 17 September, President Bola Tinubu welcomed the award, describing it as clearing the single biggest legal hurdle that had stalled the project for years.
Why it matters to practitioners
The case is one of several in which Nigeria has contested large awards or claims arising from contracts whose authorisation was disputed. Three points stand out for counsel advising states and investors.
First, authority. Where a counterparty relies on a settlement or contract signed by a ministry, the internal approvals required under Nigerian public procurement and budget rules will be tested. Investors should obtain evidence of approval at the level the law requires, not only a signature.
Second, settlements are contracts. The 2020 settlement did not end the dispute; it generated a new claim. Settlement agreements with public bodies need the same scrutiny of authority, conditions precedent and default mechanics as the original contract.
Third, costs. The costs order, and the use of ICC escrow funds, give Nigeria a recoverable sum. How and whether Nigeria enforces the balance against Sunrise will be the next step to watch.
What comes next
The award removes a legal obstacle but does not finance or build the plant. As The Rio Times observes, the next decisions concern recovery of costs and the selection of a builder and funding structure. Any challenge to the award would be brought before the French courts as the courts of the seat.