TotalEnergies and AMNI take final investment decision on the Ima gas field, Nigeria

TotalEnergies (operator, 40%) / AMNI (60%)


TotalEnergies (40%, operator) and its Nigerian partner AMNI (60%) took the final investment decision on the Ima gas field development offshore Nigeria. The field is designed to produce a plateau of 350 million cubic feet of gas per day, over 60,000 barrels of oil equivalent per day, delivered by a 22 km pipeline to Nigeria LNG, where it is expected to supply about one third of the gas needed for the Train 7 expansion. Start-up is expected in 2028.

Value: the operator did not publish a capital cost. Press reports differ (figures between US$600m and US$800m have been reported), so The Meridian records the value as not confirmed.

Advisers: no legal adviser is named in the primary announcement reviewed by The Meridian.

Sources: TotalEnergies announcement as published by Africa Oil & Gas Report, 23 September 2026; Reuters via CNBC Africa, 23 September 2026. Added to The Meridian register on 27 October 2026.