ICC tribunal awards Befesa and Standard Bank US$235m against Ghana Water over Teshie desalination plant

The tribunal upheld termination of the water purchase agreement but rejected a US$402m claim for unpaid charges as double recovery; Ghana is negotiating to buy the plant instead.


An ICC arbitral tribunal has awarded US$235m, net of taxes, to Befesa Desalination Developments Ghana Ltd and Standard Bank of South Africa against Ghana Water Company Limited (GWCL) over the Teshie-Nungua desalination plant in Accra, according to the Office of the Attorney-General. The amount includes pre-award interest to 31 March 2026, with interest continuing on the debt component from 1 April 2026. In a related arbitration under a state guarantee, the tribunal principally held the Government of Ghana liable for GWCL’s liabilities.

The claims

Befesa terminated the Water Purchase Agreement for non-payment and, with Standard Bank, commenced arbitration on 23 October 2024. The claimants sought about US$402m in unpaid charges under the agreement and about US$235m in contractual termination payments, together about US$637m. The tribunal found that Befesa had validly terminated after breaches by GWCL and that GWCL was liable for the termination payments, but dismissed the US$402m claim entirely: once the agreement was validly terminated, the contractual entitlement was the termination payment, and the claimants could not also recover unpaid charges.

The project

The plant, contracted in 2011 after an unsolicited proposal, was designed to produce 60,000 cubic metres of water a day for about 500,000 people in Teshie, Nungua and neighbouring areas. It was commissioned in April 2015, cost about US$126m to build, and has been idle. The deal was approved by Parliament in 2012 with a Ministry of Finance letter of comfort.

What happens next

The Attorney-General says the government is in advanced negotiations to acquire the plant from Befesa for a price significantly below the award, and aims to restore supply to an estimated one million residents in eastern Accra.

Get the next Meridian Briefing. Every Thursday at 11:00 WAT.

Lessons

The award follows a familiar pattern in West African take-or-pay utility contracts: a state utility unable to pay capacity charges, a sovereign guarantee, and termination payments calculated to repay lenders and equity. The tribunal’s refusal to allow unpaid charges and termination compensation cumulatively is a useful precedent for states, but the guarantee turned a utility default into a sovereign liability. Governments negotiating independent water and power projects should scrutinise termination payment formulas, guarantee scope and demand forecasts, particularly for unsolicited proposals. Settlement by acquisition of the asset is a pragmatic route where the plant is useful and lenders need an exit.