Launched 15 November 2023 by President Akufo-Addo and completed under President Mahama in November 2025, Phase 2 of the Meridian Port Services (MPS) Terminal 3 project delivered 270,000m² of yard, 15 STS cranes and electric RTGs, four berths and a 1.4km quay across 127 hectares, lifting Tema’s capacity from 2.5m to 3.7m TEU. MPS is the JV of APM Terminals 35%, Africa Global Logistics (MSC) 35% and Ghana Ports & Harbours Authority 30%, Ghana’s defining PPP, with Phase 2 alone valued at US$150m by AGL and the overall expansion programme valued at ~US$1.5bn by Ghana’s Transport Ministry.
Tema handled 2.2m TEU in 2025, ahead of Abidjan (1.6m) and Lomé (2.06m in 2024).
Value: ~US$1.5bn (verified against public announcements).
Advisers: No legal adviser is identified in the public record reviewed by The Meridian.
Recorded by The Meridian research desk from public announcements, regulatory filings and financial press coverage. Dates and values are as publicly reported.